Renovation Permits in Winnipeg: What Needs One and How to Apply

A project-by-project guide to City of Winnipeg building, development, electrical and plumbing permits for home renovations, checked against the City’s own pages.

Permits are the part of a renovation most people would rather skip, but in Winnipeg they’re also how the work gets checked by an inspector before it disappears behind drywall. This guide sorts common home projects into what needs a permit and what doesn’t, using the City of Winnipeg’s own pages, checked on October 13, 2026. Rules change, so treat it as a starting point and confirm your project with the City’s Permits Direct Line at 204-986-5140.

Which renovations need a building permit in Winnipeg?

The City’s home renovations page lists kitchens, bathrooms, adding or converting rooms to bedrooms, creating open-concept living space, and new or larger exterior door or window openings as work that may need a building permit under the Winnipeg Building By-law. Since February 2026, the By-law requires one to create a new bedroom or finish a previously undeveloped level. Basements, additions, higher decks, larger sheds and garages, and secondary suites need one too.

Common Winnipeg home projects and the permits they usually need
ProjectBuilding permit?Also check
Painting, flooring, cabinets, shelves, millworkNoBuilding code and zoning still apply
Replacing doors and windows with the same sizeNoSame size only; see window and door replacement in Winnipeg
New or larger exterior door or window openingYesA development permit may apply; new or enlarged openings in a foundation wall need engineer-stamped drawings
Kitchen or bathroom renovationOften; the City lists bothPlumbing and electrical permits for any changes to those systems
Removing walls for an open-concept layoutYesExpect structural drawings if load-bearing walls, beams or joists change
Finishing a basement (rooms, bedrooms, living space)YesSee basement development permits
Secondary suiteYesDevelopment permit, plus electrical and plumbing permits
Addition or attached garageYesDevelopment permit and zoning; see home additions and zoning
Deck more than 600 mm (2 ft.) above ground and over 3.4 m² (36 sq. ft.)YesOpen decks under 600 mm don’t need a permit
Detached shed, garage or other accessory structure over 10 m² (108 sq. ft.)YesSeparate electrical permit for detached garages and carports
Sump pit when adding or replacing weeping tileYesPlumbing permit for the backwater valve; electrical permit for the pump’s dedicated receptacle
Re-shingling or re-siding with the same materialNoCode still applies

Sources: City of Winnipeg home renovations, home improvement projects, decks and accessory structures pages, and Information Bulletin 2025-001, checked October 13, 2026.

What doesn’t need a permit?

The City lists these as projects that typically don’t need a permit: barrier-free ramps, fences on single- and two-family lots, replacing stucco, siding or shingles with the same material, small detached accessory structures, low open decks, interior finishing work, and same-size door and window replacement. Building code and zoning rules still apply.

The limits matter. Detached accessory structures have to be under 10 m² (108 sq. ft.), open decks under 600 mm (2 ft.) high, and interior work means painting, patching, decorating or installing cabinets and shelves.

Trade work has its own exemptions. In an owner-occupied single detached house, swapping a light fixture, switch or receptacle in the same location doesn’t need an electrical permit, as long as the existing copper branch circuit isn’t modified. Repairing a leak or replacing a fixture such as a faucet or water heater in the same location doesn’t need a plumbing permit if the system itself isn’t changed. Moving or adding outlets, circuits or drains does.

Do you also need a development permit?

Sometimes. A development permit checks zoning, such as land use and where a structure sits on the lot; a building permit checks construction against code. Secondary suites, additions and some exterior changes can need both. Confirm before you apply, because the City’s forms warn that a building permit will be refused if a development permit was needed.

If the project involves a basement or lower-level suite, the rules are stricter than for a rec room. Our guide to secondary suite rules in Winnipeg covers what the City asks for.

How do I apply for a development permit in Winnipeg?

Confirm whether you need one, then apply through Permits Online. Since October 2025 the City reviews development and building permit applications at the same time for projects that need both (concurrent review); you can still wait for development approval before applying for the building permit (sequential review). The building permit must match the development approval.

  1. Ask the City whether your project needs a development permit: call Permits Direct Line at 204-986-5140 or email ppd-zdo@winnipeg.ca to reach a Zoning Development Officer.
  2. Prepare the development permit application and the City’s checklist for your type of building; there is one for single- and two-family residential properties.
  3. Submit it through Permits Online, or drop it off at the Zoning & Permits office, Unit 31-30 Fort Street, weekdays 8:30 a.m. to 4:30 p.m.
  4. Choose concurrent or sequential review when you apply for the building permit.
  5. If your project is exempt, include the City’s declaration form for development permit exemption with the building permit application.

Who takes out the permit: you or your contractor?

The City says homeowners are responsible for getting permits before a project starts, and that if you hire a contractor, you should make sure the permit is in place before work begins. In other words, the responsibility stays with you even when someone else fills in the forms, so ask to see the permit.

Trade permits have their own rules. Electrical and plumbing permits go to licensed contractors, or to a homeowner who does the work personally in the single detached house that is their primary residence. Homeowners can’t take out electrical permits for some work, including electrical services, work over 200 amps, generators and EV chargers.

On our projects, permits and inspections are coordinated with the City of Winnipeg or the local municipality, and your written quote spells out what’s included. Whoever you hire, ask the same question before you sign.

How long does a Winnipeg permit take?

There’s no single number. The City publishes building permit processing times, measured in average business days to confirm a complete application and to reach a decision. Incomplete applications are delayed, so complete, dimensioned drawings are the part of the timeline you control.

What inspections should you expect?

Permitted work is inspected before it’s covered. Request inspections through the City’s housing inspection request form at winnipeg.ca/housinginspection, or by phone at 204-986-5300 on weekdays. Insulated walls and ceilings get a rough-in inspection and then a preboard inspection of insulation and vapour barrier before drywall. Wiring and plumbing are inspected before they’re covered too.

What happens if you renovate without a permit?

The City’s Permit Amnesty page says renovations done without permits must be brought up to current codes through permits and inspections, that post-construction penalty fees are waived only where amnesty is approved, and that undeclared work can lead to notices or orders, with fines or penalties. Amnesty covers a homeowner’s primary residence, not rental properties.

In practice, a missing permit can mean opening finished walls so an inspector can see what’s inside, adding cost and delay at the end of a project.

Which building code applies in Manitoba?

Manitoba adopted the 2020 editions of the national model building, plumbing, energy and fire codes effective January 1, 2024. Building and plumbing permits approved from that date are reviewed against the 2020 codes, while inspections on permits approved earlier check the plans approved under the previous codes.

Renovating outside Winnipeg?

Permits come from the municipality where the house is. Around Winnipeg, that means the RM of Headingley; the Red River Planning District for East St. Paul and West St. Paul; the RM of Macdonald for Oak Bluff; and the cities of Selkirk and Steinbach. Requirements and forms differ, so confirm the permit office and its process before you finalize drawings.

Next step

Permit questions are easier to answer with the space in front of you, whether you’re planning a kitchen renovation, a bathroom renovation or an addition. Every project starts with a free on-site visit and a free written quote, so book your visit, or get a starting range first with our instant estimate. For budgets, see the Winnipeg renovation cost guide.

Frequently Asked Questions

A detached accessory structure, such as a shed, of 10 m² (108 sq. ft.) or less doesn’t need a building permit in Winnipeg; the City requires one above that size. Smaller structures still have to meet zoning rules such as setbacks, and electrical work in them needs its own permit. Outside Winnipeg, check with your municipality.

Planning a project like this in Winnipeg?

Tell us what you have in mind and we will put together a clear, written quote.

GET FREE INSTANT QUOTESee our Kitchen Renovations

or call 431-866-5644

← Back to all articles

Get a free instant quote

Answer a few quick questions for a starting price range, then book a free on-site visit for your written quote.